    Verification

    How Vigilbase OS checks that an approved change persisted, had its intended security effect and caused no harm.

    Vigilbase OS is in preview. Features and connectors are still being validated with customers and may change before general availability.

    A successful API response does not prove that a fix worked. After an approved plan runs, Vigilbase OS verifies each step against criteria that were fixed when the plan was proposed and that the approver saw before approving.

    Three layers

    Each verification run checks three layers:

    LayerQuestion
    Configuration persistedIs the change actually in place when Vigilbase reads the provider back?
    Security effect observedDid the change have the intended effect, for example blocked requests attributed to a new WAF rule?
    Operational guardrailsDid service health stay acceptable, for example the edge error rate compared with a baseline?

    The plan sets the observation window, baseline period, minimum sample size and success and failure thresholds for each step. You see them under Verification criteria on the plan before you approve.

    Outcomes

    OutcomeMeaning
    PendingVerification is scheduled or the observation window is still open.
    VerifiedThe change persisted, had its intended effect and stayed within guardrails.
    FailedThe change did not persist or did not have its intended effect.
    HarmfulThe change caused a problem that the guardrails detected.
    InconclusiveThere was not enough evidence, for example no traffic or a disconnected feed.

    No traffic and missing telemetry always give Inconclusive, never Verified.

    When something goes wrong

    • Recovery steps run only if the approver included them when approving, and only when the forward step fails or verification finds harm. Any other recovery change goes back through approval.
    • Unknown outcomes are never blindly retried. If Vigilbase cannot tell whether a provider accepted a change, the step shows Unknown while Vigilbase reconciles the provider's actual state.
    • Partial success is recorded per step. Changes across several providers are not atomic, so a plan can end Partially succeeded, and only approved recovery steps may run.

    Each execution is an immutable record with the provider state before and after each step. See Approvals.